26 September 2021

Week results in the project "Duyunov's motors"

26 September 2021

The main news of the week in the project: the installation of the metal frame for the "Sovelmash" D&E has been completed. It took less than 4 months for the specialists of the subcontractor Astron to build it. 
 
 Besides, the installation of the building basement panels, the laying of profiled sheets and waterproofing for casting the interfloor slabs have been completed. The next step is to mount the reinforcement mesh and install the frames for pouring concrete. Some more construction activities are also underway. Everything possible is being done to close the thermal circuit of the building before the cold weather. 
 
 The news story "Sovelmash" VS Tesla" was published in Zelenograd district newspaper "41". The publication reports on the questionable Tesla authorship of the heat pump development for heating the interior of electric cars. However, eight years earlier, this invention was patented by "ASiPP".
 The electronic version of the publication is available here https://id41.ru/upload/iblock/34e/34_sborka_web.pdf , on page 12. 
 
 Follow the news of the project "Duyunov's motors"!

Also read

"Sovelmash" work routine | Latest news from the construction site and leased premises

In the new video, Alexander Sudarev tells about the work routine at "Sovelmash".

19 October 2021

Including "Sovelmash" in the implementation of the development plan for producing electric vehicles in Russia

"Sovelmash" is preparing a package of documents on induction motors for the Department of Mechanical Engineering of the Russian Federation.

18 October 2021

Week results in the project "Duyunov's motors"

The main events of the last week in the project took place at the construction site.

17 October 2021

Overview of construction activities from the start until today | Construction of "Sovelmash" D&E

Let's remember how the construction process progressed from the beginning to the present moment.

12 October 2021