How is pouring the first-level floor in the "Sovelmash" D&E building progressing?
22 九月 2022
Step by step, the floor in the "Sovelmash" D&E is brought to "zero".
🔹 Over 70% of waterproofing on the first floor of the O&A (office and amenity) building has been completed, axes 1-6.
🔹 80% of waterproofing in the production part of the building has been completed, axes 17-23.
🔹 In axes 6-17, the waterproofing is 100% complete, the protective waterproofing layer - 100% complete, the ground loop - 100% complete, the reinforced concrete - 27% complete.
Yesterday the foundations for four high-voltage transformers were cast, as well as the foundations for the motors in the anechoic chamber.
This coming Friday, all of the rebar in the photo will be cast in concrete.
Employees of the contracting company work daily until late in the evening. They work in a well-coordinated and professional way. A short lunch break and back to work again.
也可讀取
The features for conversion of shares are ready to be launched in the back office
Find out who will get access first.
19 四月 2024
Withdrawing the opportunity to restore installment plans cancelled in 2018
Withdrawing the opportunity
18 四月 2024
Project news and results: live broadcast with the SOLARGROUP management
The link to the broadcast can be found inside.
17 四月 2024