Results of the week in the project "Duyunov's motors"

5 五月 2024

"Sovelmash" D&E construction

During the public holidays, the construction activities at the "Sovelmash" site continued at a brisk pace.

• The engineering networks, namely ventilation, cooling systems, and electricity, were installed.
• The strapping of the dry cooling towers, which are part of the building's cooling system, was completed. Pressure testing and insulation are next, followed by fencing and a canopy.
• Finishing of the entrance unit and cladding of the entrance from the outside with granite tiles was in progress.
• Installation of the piles that will support part of the fence in the ‘steep’ slope area and the gate started.
• The elevators on the first floor of the office and amenity building got a finished look.
• Casting the foundations for the noise shield supports continued.

Meanwhile, development and preparation for production of the "Sovelmash" products, namely parts of the ordered motor, was underway.

Current offers

Let us remind you of the offers that will add value to your investment in the project.10% discount on payments of $ 100 or more for early repayment until May 31 inclusive.

Information about all the offers in the project is available in the back office.

Make use of it!

INVEST

也可讀取

More data on funding the project "Duyunov's motors"

What's new on the roadmap?

16 五月 2024

"I have tested “Slavyanka” based motors!"

Andrey Lobov conducted a test drive for the guests from Vietnam

14 五月 2024