Results of the week in the project "Duyunov's motors"

14 jul 2024

"Sovelmash" D&E construction

• Flooring was installed on the third floor of the building.
• Work was underway on the ventilation utilities.
• The installation of a noise shield on the border with the gardening association was completed.
• Excavation work began to reconstruct the chamber of the second water supply inlet.
• Asphalt paving and landscaping work was underway.
• The pedestrian entrance was mounted on the premises.

Thanks to the professionalism of its employees, "Sovelmash" has once again recovered 25 million rubles in VAT.

Current offers

5% discount on payments of $ 100 or more for early repayment up to and including August 31.
Friendly promo code for 10% of bonus shares when buying a new package until the end of stage 19.

Information about all the offers in the project is available in the back office.

Take advantage of the offers and invest in the "Sovelmash" engineering business with maximum benefits!

INVEST

Also read

Како инвестирати у дирижабле на најповољнији начин до краја 3. фазе

Погледајте избор промотивних понуда и искористите их благовремено!

29 jun 2026

Једноставно упутство: од избора начина до безбедног преноса средстава

Корак по корак и без компликованих термина

25 jun 2026