14 七月 2024
Results of the week in the project "Duyunov's motors"
14 七月 2024
"Sovelmash" D&E construction
• Flooring was installed on the third floor of the building.
• Work was underway on the ventilation utilities.
• The installation of a noise shield on the border with the gardening association was completed. 
• Excavation work began to reconstruct the chamber of the second water supply inlet. 
• Asphalt paving and landscaping work was underway. 
• The pedestrian entrance was mounted on the premises.
Thanks to the professionalism of its employees, "Sovelmash" has once again recovered 25 million rubles in VAT.
Current offers
• 5% discount on payments of $ 100 or more for early repayment up to and including August 31. 
• Friendly promo code for 10% of bonus shares when buying a new package until the end of stage 19.  
Information about all the offers in the project is available in the back office.
Take advantage of the offers and invest in the "Sovelmash" engineering business with maximum benefits!
也可讀取
Meet with the «AERONOVA» team at Dubai Airshow 2025 — discuss the future of airships in person!
How to schedule a meeting
24 十月 2025
Finish strong: receive a payout for upgrading your status through November 4!
Reminder of the terms
23 十月 2025
From idea to landing page in a day: how to create a high-converting website with AI | Earn with neuro
Overview of tools for SOLARGROUP partners
22 十月 2025