Summing up the interim construction results in numbers. Previously, we did it in mid-November 2023, see to understand the progress.

What has been done?

Over the first 2 years of the construction efforts, the thermal circuit of the building was completed, namely foundation, frame, walls, roofing, windows, doors and intermediate floors.

Over the third year, external engineering networks were completed and most of the territory was landscaped, interior finishing and commissioning of the process equipment started.

Currently, the degree of completion for the engineering networks is as follows:

• wastewater sewage — 100%,
• storm water drainage — 100%,
• firefighting — 99%,
• heating system — 90%,
• ventilation — 50%,
• cold water supply — 40%,
• smoke extraction — 20%.

The interior finishing of the office and amenity complex is 75% complete.

Assessing the exact degree of completion for some tasks is difficult and too labor-intensive, so the figures are approximate

What is to be completed?

In addition to the above, the interior finishing of the production building and landscaping of the area must be completed. Noise-absorbing barriers are also to be installed on the site.

Looking forward to 100% completion of all the construction activities? Invest in the project yourself and invite new investors!

INVEST

也可讀取

Project Guide: Why is it important to repay your installment plan in full?

The calculations of your benefit can be found inside.

7 五月 2024

The most beneficial offer of May in the project

Answering the most frequently asked questions.

6 五月 2024

Results of the week in the project "Duyunov's motors"

Find out about the key events.

5 五月 2024