22 září 2022
How is pouring the first-level floor in the "Sovelmash" D&E building progressing?
22 září 2022
Step by step, the floor in the "Sovelmash" D&E is brought to "zero".
🔹 Over 70% of waterproofing on the first floor of the O&A (office and amenity) building has been completed, axes 1-6.
🔹 80% of waterproofing in the production part of the building has been completed, axes 17-23.
🔹 In axes 6-17, the waterproofing is 100% complete, the protective waterproofing layer - 100% complete, the ground loop - 100% complete, the reinforced concrete - 27% complete.
Yesterday the foundations for four high-voltage transformers were cast, as well as the foundations for the motors in the anechoic chamber.
This coming Friday, all of the rebar in the photo will be cast in concrete.
Employees of the contracting company work daily until late in the evening. They work in a well-coordinated and professional way. A short lunch break and back to work again.
Čtěte také
What has been improved in the back office?
It has become even more convenient to use our promo offers
25 dubna 2024
The world continues to discover the "Slavyanka" technology
How did the live meetings in India go?
24 dubna 2024