22 září 2022
How is pouring the first-level floor in the "Sovelmash" D&E building progressing?
22 září 2022
Step by step, the floor in the "Sovelmash" D&E is brought to "zero".
🔹 Over 70% of waterproofing on the first floor of the O&A (office and amenity) building has been completed, axes 1-6.
🔹 80% of waterproofing in the production part of the building has been completed, axes 17-23.
🔹 In axes 6-17, the waterproofing is 100% complete, the protective waterproofing layer - 100% complete, the ground loop - 100% complete, the reinforced concrete - 27% complete.
Yesterday the foundations for four high-voltage transformers were cast, as well as the foundations for the motors in the anechoic chamber.
This coming Friday, all of the rebar in the photo will be cast in concrete.
Employees of the contracting company work daily until late in the evening. They work in a well-coordinated and professional way. A short lunch break and back to work again.
Čtěte také
Don't miss out on up to 20% cashback on cryptocurrency top-ups
The promotion is ending!
24 dubna 2026
Dmitry Duyunov on the production of the first batch of angle grinders, challenges with the supply of machine tools and metal
Overview of the "Expert Time" episode of April 16
21 dubna 2026
Cryptocurrency without stress: how to fund your account when traditional methods don’t work
And receive up to 20% cashback for doing so
21 dubna 2026