How is pouring the first-level floor in the "Sovelmash" D&E building progressing?
22 septembar 2022
Step by step, the floor in the "Sovelmash" D&E is brought to "zero".
🔹 Over 70% of waterproofing on the first floor of the O&A (office and amenity) building has been completed, axes 1-6.
🔹 80% of waterproofing in the production part of the building has been completed, axes 17-23.
🔹 In axes 6-17, the waterproofing is 100% complete, the protective waterproofing layer - 100% complete, the ground loop - 100% complete, the reinforced concrete - 27% complete.
Yesterday the foundations for four high-voltage transformers were cast, as well as the foundations for the motors in the anechoic chamber.
This coming Friday, all of the rebar in the photo will be cast in concrete.
Employees of the contracting company work daily until late in the evening. They work in a well-coordinated and professional way. A short lunch break and back to work again.
Also read
Искористите прилику да остварите до 20% кешбека за допуну криптовалутом
Акција се завршава!
24 april 2026
Дмитриј Дујунов о производњи прве партије угаона брусилица, изазовима у испорукама обрадних машина и метала
Преглед емисије „Време за стручњаке“ од 16. априла
21 april 2026
Криптовалута без стреса: како допунити рачун, када уобичајене методе не функционишу
И добити за то кешбек до 20%
21 april 2026