22 September 2022
How is pouring the first-level floor in the "Sovelmash" D&E building progressing?
22 September 2022
Step by step, the floor in the "Sovelmash" D&E is brought to "zero".
🔹 Over 70% of waterproofing on the first floor of the O&A (office and amenity) building has been completed, axes 1-6.
🔹 80% of waterproofing in the production part of the building has been completed, axes 17-23.
🔹 In axes 6-17, the waterproofing is 100% complete, the protective waterproofing layer - 100% complete, the ground loop - 100% complete, the reinforced concrete - 27% complete.
Yesterday the foundations for four high-voltage transformers were cast, as well as the foundations for the motors in the anechoic chamber.
This coming Friday, all of the rebar in the photo will be cast in concrete.
Employees of the contracting company work daily until late in the evening. They work in a well-coordinated and professional way. A short lunch break and back to work again.
Also read
30 days until the Dubai Airshow! AERONOVA looks forward to seeing you in Dubai!
Get a promo code for a free ticket
17 October 2025
Attend Dubai's premier airshow — with SOLARGROUP!
Learn how to obtain an invitation to Dubai Airshow 2025
16 October 2025
Promotion for SOLARGROUP partners: "Hunting" extended!
Attract leaders — increase your income!
13 October 2025