22 September 2022

How is pouring the first-level floor in the "Sovelmash" D&E building progressing?

22 September 2022

Step by step, the floor in the "Sovelmash" D&E is brought to "zero".

🔹 Over 70% of waterproofing on the first floor of the O&A (office and amenity) building has been completed, axes 1-6. 
🔹 80% of waterproofing in the production part of the building has been completed, axes 17-23. 
🔹 In axes 6-17, the waterproofing is 100% complete, the protective waterproofing layer - 100% complete, the ground loop - 100% complete, the reinforced concrete - 27% complete.

Yesterday the foundations for four high-voltage transformers were cast, as well as the foundations for the motors in the anechoic chamber.

This coming Friday, all of the rebar in the photo will be cast in concrete.

Employees of the contracting company work daily until late in the evening. They work in a well-coordinated and professional way. A short lunch break and back to work again.

READ ALL NEWS

Also read

News of the latest negotiations

Find out who is interested in the services and products offered by "Sovelmash"

26 March 2024

Find out about the completion status of the engineering centre

Interim construction results in numbers.

25 March 2024