22 január 2023
Results of the week in the project "Duyunov's motors"
22 január 2023
Last week, various activities were in progress at the "Sovelmash" construction site.
• A new stage began: getting the D&E production area ready for work. The winding equipment was being installed there, the crane beams were being welded in place, and the cleanup of the area began.
• In the office and amenity building, the installation of engineering systems, electrical outlets and sockets continued.
• The interior partitions were being installed.
• The delivery of the engineering and process equipment to the D&E territory was underway.
• Outside the building, the earthwork was carried out to install the sewerage and connect the building to the heating pipeline.
On January 16, the project entered a new funding stage 18 out of the 20 planned ones. The project is nearing completion, but you can still become a co-owner of the "Sovelmash" engineering enterprise on beneficial conditions, which will not be available once the funding is completed. Invest in the project, support the D&E construction and get dividends from its activities.
Čítajte tiež
Withdrawing the opportunity to restore installment plans cancelled in 2018
Withdrawing the opportunity
18 apríl 2024
Project news and results: live broadcast with the SOLARGROUP management
The link to the broadcast can be found inside.
17 apríl 2024
Project guide: how do I top up my account in the back office?
Manual and important details.
16 apríl 2024