22 January 2023

Results of the week in the project "Duyunov's motors"

22 January 2023

Last week, various activities were in progress at the "Sovelmash" construction site. 

• A new stage began: getting the D&E production area ready for work. The winding equipment was being installed there, the crane beams were being welded in place, and the cleanup of the area began. 
• In the office and amenity building, the installation of engineering systems, electrical outlets and sockets continued. 
• The interior partitions were being installed. 
• The delivery of the engineering and process equipment to the D&E territory was underway.
• Outside the building, the earthwork was carried out to install the sewerage and connect the building to the heating pipeline. 

On January 16, the project entered a new funding stage 18 out of the 20 planned ones. The project is nearing completion, but you can still become a co-owner of the "Sovelmash" engineering enterprise on beneficial conditions, which will not be available once the funding is completed. Invest in the project, support the D&E construction and get dividends from its activities.

MORE NEWS

Also read

What does a customer want? Case study of a partner's experience

I'll solve a difficult problem in the easiest way possible

24 July 2024

What opportunities will be closed to investors?

Learn about the project's development plans

22 July 2024

Results of the week in the project "Duyunov's motors"

Find out about the key events

21 July 2024