22 January 2023

Results of the week in the project "Duyunov's motors"

22 January 2023

Last week, various activities were in progress at the "Sovelmash" construction site. 

• A new stage began: getting the D&E production area ready for work. The winding equipment was being installed there, the crane beams were being welded in place, and the cleanup of the area began. 
• In the office and amenity building, the installation of engineering systems, electrical outlets and sockets continued. 
• The interior partitions were being installed. 
• The delivery of the engineering and process equipment to the D&E territory was underway.
• Outside the building, the earthwork was carried out to install the sewerage and connect the building to the heating pipeline. 

On January 16, the project entered a new funding stage 18 out of the 20 planned ones. The project is nearing completion, but you can still become a co-owner of the "Sovelmash" engineering enterprise on beneficial conditions, which will not be available once the funding is completed. Invest in the project, support the D&E construction and get dividends from its activities.

MORE NEWS

Also read