22 Январь 2023
Results of the week in the project "Duyunov's motors"
22 Январь 2023
Last week, various activities were in progress at the "Sovelmash" construction site.
• A new stage began: getting the D&E production area ready for work. The winding equipment was being installed there, the crane beams were being welded in place, and the cleanup of the area began.
• In the office and amenity building, the installation of engineering systems, electrical outlets and sockets continued.
• The interior partitions were being installed.
• The delivery of the engineering and process equipment to the D&E territory was underway.
• Outside the building, the earthwork was carried out to install the sewerage and connect the building to the heating pipeline.
On January 16, the project entered a new funding stage 18 out of the 20 planned ones. The project is nearing completion, but you can still become a co-owner of the "Sovelmash" engineering enterprise on beneficial conditions, which will not be available once the funding is completed. Invest in the project, support the D&E construction and get dividends from its activities.
Also read
Bringing back the "Gift to a Friend" option from February 1
We have heeded your requests and are launching the "Gift to a Friend" option on February 1.
01 Февраль 2023
I now earn more than I could imagine | Story of SOLARGROUP partner Faizan Khan, India
My name is Faizan Khan.
30 Январь 2023
Results of the week in the project "Duyunov's motors"
What happened in the project "Duyunov's motors" last week?
29 Январь 2023