22 јануари 2023
Results of the week in the project "Duyunov's motors"
22 јануари 2023
Last week, various activities were in progress at the "Sovelmash" construction site.
• A new stage began: getting the D&E production area ready for work. The winding equipment was being installed there, the crane beams were being welded in place, and the cleanup of the area began.
• In the office and amenity building, the installation of engineering systems, electrical outlets and sockets continued.
• The interior partitions were being installed.
• The delivery of the engineering and process equipment to the D&E territory was underway.
• Outside the building, the earthwork was carried out to install the sewerage and connect the building to the heating pipeline.
On January 16, the project entered a new funding stage 18 out of the 20 planned ones. The project is nearing completion, but you can still become a co-owner of the "Sovelmash" engineering enterprise on beneficial conditions, which will not be available once the funding is completed. Invest in the project, support the D&E construction and get dividends from its activities.
Исто така прочитајте
Станете дел од историјата на проектот „Цепелини од новата генерација“
Дознајте ја уникатноста на подарокот
12 септември 2025
Започнете со 25$ и искористете 10% попуст на инвестициите!
Дознајте ги промоциите за нови инвеститори
9 септември 2025
Цепелини за достава во тешко достапни региони: спасување на планетата од небото
Наскоро за ова ќе зборуваат сите
8 септември 2025